Microsoft Project Work Equation and Task Types
Microsoft Project Work Equation
Introduction
When assigning resources to tasks, Microsoft Project uses a simple formula to calculate how long each task will take, given the specified number of resources. This formula can be written as:
Duration = Work / Units
Where:
- Duration
- The calculated amount of time it will take to complete the task.
- Work
- The amount of time (usually expressed in hours or days) that it would take one person to complete the task if they were working at it full time every day.
- Units
- If a person is said to spend 100% of their time at work then this is the amount of time that they spend working on this project. Units are expressed as a percentage or a decimal. Thus if they are available to spend their whole time working on task then Unit would be 100% or 1.0. If they are only available to spend half their time on a project then Unit would be 50% or 0.5
Thus if it takes one man working full time 8 hrs to build a wall the duration of the task will be:
Duration = work / unit = 8 hrs / 1 = 8 hrs
Duration = 8hrs
Whereas if he is only available to spend 50% of his time on the task
Duration = work / unit = 8 hrs / 0.5 = 16hrs
Duration = 16hours or 2 days
And if there are two men working full time then
Duration = 8 hrs / 2 = 4 hrs
Task Types
Microsoft Project gives us some control over what happens to tasks when we change Duration, Work or Units. There are three task types:
- Fixed Units
- Fixed Work
- Fixed Duration
In these instances the word Fixed means that, of the three variables, Project will keep one constant, so that if we change the second Project will automatically change the third to ensure that the formula remains correct.
For example if a task is Fixed Duration, with a Duration of 8 hours, Work of 8 hours and Unit of 1.0, then we know from the above formula that
Duration = Work / Unit
8 = 8 / 1
If we now change the number of units available to work on the task to 0.5 then the amount of Work needs to change, because it is a fixed duration task.
Since the duration must stay the same at 8hours
8 hours (Duration) = ? hours(Work) / 0.5
Work = 8 (Duration) * 0.5 = 4
Work = 4 hours
Summary
The relationships between the task types and the impact of changing one variable on the other, is shown in the following table.
Task TypeYou ChangeDurationUnitsWork
Project will change
Fixed DurationWorkWorkUnitsFixed UnitsWorkDurationDurationFixed WorkUnitsDurationDuration |
---|